Be honest with iteration time

Closing the iteration, on time, is one of key success for software project plan. Assume we have X features planned for iteration Y. At the end of iteration X, the project manager/team leader and process engineer [and customer in some cases] are supposed to review the iteration. Usually they evaluate the features and mark them as finished or not. If some of the features are still under development, never, ever extend the iteration duration. Drop the remaining features and close the iteration.

Instead of extending the duration, close it, and do the following things:

  • Investigate why the features are not finished
  • Work on improving the time estimate
  • Monitor the time estimation in different iteration
  • Most of the time, it's not developers' fault if they have not finished on time, it's because of bad estimation

It happens a lot the estimates at the begriming of the iterations are wrong. The key point at the end of iteration is dropping the remaining features and closing the iteration on time instead of extending the time of iteration.

Tuesday, October 24, 2006

SharePoint 2007, Wooooow

I got a chance to have a look to MS SharePoint 2007 Beta 2. Thanks to SharePoint team to the big improvement of user interface.
For me, it was a huge difference.
Different types of web sites, having more user interface to make web master's life easier and easier ways to share data among sub sites, are the most visible features.

Check here for Microsoft Office SharePoint Server 2007 Evaluation Guide.
Check here for Microsoft Office SharePoint Server 2007